DPS/Building Construction - Use and Occupancy

WHEN IS A USE & OCCUPANCY CERTIFICATE REQUIRED?

A Use & Occupancy Certificate is required for the space to be used prior to opening any business in Montgomery County.

The purpose of this certificate is to document that the use is permitted, and that all applicable safety code and health code requirements have been met.

WHAT IS THE APPLICATION PROCESS?

  • Submit a completed Use and Occupancy application accompanied by one copy of a site plan showing parking analysis. If the property is located within the parking lot district of Bethesda, Silver Spring, Wheaton, or Montgomery Hills, no site plan is needed because these areas are provided with public parking.
  • For food service establishments, submit a completed Statement of Operations form.
  • If the use is permitted by special exception, submit a copy of the current special exception opinion.

APPROVALS AND INSPECTIONS REQUIRED

  • The zoning official must approve your site for the use intended.
  • The property must be inspected and approved by the Fire Marshal, and by the building, mechanical and electrical inspectors. To schedule your Use and Occupancy inspections, please call 240-777-6370. Use and Occupancy inspection requests are not accepted through the DPS web site or the DPS Interactive Voice response (IVR) system.
  • If the use is permitted by special exception, a zoning inspection is also required

WHAT IS THE COST OF THE CERTIFICATE?

Fees From Schedule of Fees for Permits, Licenses and Certifications (Executive Regulation 15-03AM) Department of Permitting Services Costs:

  1. The fee for a Use-and-Occupancy Certificate must be paid at the time of application. The maximum fee is $590.
  2. The fee for any Use-and-Occupancy Certificate for each building or portion of a building or use is per square foot of area, as follows:
    0 - 5,000 SF $215
    5,001 - 10,000 SF $355
    10,001 - 20,000 SF $425
    20,001 SF and up $425 plus $.0118 SF of area exceeding 20,000 SF
  3. The fee for a Use-and-Occupancy Certificate for lots or parcels without buildings/structures on them is $215.
  4. The inspection fee for using or occupying a site without a Use-and-Occupancy Certificate is $88, in addition to the fee for the Use-and-Occupancy Certificate.

Fees from Fire Safety Code – Fee Schedule for Permits, Licenses and Exceptions (Executive Regulation 18-03)

Use and Occupancy Fees, Other Inspection Fees

Fees for Use and Occupancy or other inspections not covered by other sections of this regulation, except enforcement generated inspections:
a. 0 - 5,000 SF $180
b. 5,001 - 10,000 SF $300
c. 10,001 - 20,000 SF $360
d. 20,001 SF and up $360 plus $.01 per sq. ft.
e. The fee for a use and occupancy fire code inspection must be paid at the time of application. The maximum fee is $5,000.00.

An additional 10% Automation Enhancement Fee is charged on the cost(s) listed above.

WHAT IF THE SPACE WAS PREVIOUSLY OCCUPIED?

  • If the use of the space has not changed (e. g., a business office moves out and another business office moves in), there may be a Use & Occupancy Certificate on file in our office, and a new use an occupancy certificate is not required.
  • If the use or dimensions of the space have changed, a new Use & Occupancy Certificate is required.

IF THE PREVIOUS OWNER/TENANT DID NOT LEAVE THE CERTIFICATE, HOW CAN I GET A COPY?

Copies of certificates can be obtained from this office by completing a Request for Information form.

HOW LONG IS THE CERTIFICATE VALID?

The certificate is valid until the use of the space changes or there is an increase or decrease in the floor area used.


USE AND OCCUPANCY CERTIFICATE PROCESS AT A GLANCE